NEW QUESTION 34
For which planning-relevant data objects do you set just one indicator to include then in PP/DS?
There are 2 correct answers to this question.
Response:
- A. Material
- B. Plant
- C. Production version
- D. Work center
Answer: A,D
NEW QUESTION 35
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?
- A. When the MRP results are saved
- B. When you create a sales order
- C. When you create a planned order
- D. When you deliver a sales order
Answer: B
NEW QUESTION 36
What is the correct sequence of the following Activate methodology phases?
Please choose the correct answer.
Response:
- A. Prepare, Explore, Realize, Deploy
- B. Prepare, Realize, Iterate, Continuous Improvement
- C. Validate, Realize, Test , Deploy
- D. Prepare, Validate, Test, Go-Live
Answer: A
NEW QUESTION 37
What does the industry sector determine? Note: There are 2 correct answers to this question.
- A. Whether a material master field is required, changeable, displayed, or hidden
- B. Which material master views can be maintained
- C. Whether material numbers are assigned internally or externally
- D. Which transaction you can use to create a new material
Answer: A,B
NEW QUESTION 38
In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars indicate?
Please choose the correct answer.
Response:
- A. The priority of the proposed solution
- B. The viability of the proposed solution
- C. The presence of firmed planned orders
Visit us athttp://examcertify.com/C_TS422_1909.html - D. The presence of production orders
Answer: B
NEW QUESTION 39
Which of the following is an advantage of MRP Live and NOT available in classical MRP?
Response:
- A. MRP Live can priorities demand from sales orders
- B. MRP Live can create production orders automatically
- C. MRP Live can plan materials with recursive BOMs
- D. MRP Live can propose alternative solutions
Answer: D
NEW QUESTION 40
What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:
- A. It is a simplified form of production control
- B. Replenishments are based on centralized planning
- C. It is mostly accomplished by manual postings
- D. Replenishments are created close to the actual need
Answer: A,D
NEW QUESTION 41
Which materials have a negative quantity in a bill of materials or in a recipe? Note: There are 3 correct answers to this question.
- A. Continuous flow materials
- B. Co-products
- C. Waste products
- D. By-products
- E. Bulk materials
Answer: B,C,D
NEW QUESTION 42
The procurement type of your material is set to "E" for In-house production. Which of the following is valid to determine a source of supply in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Selection Method
- B. Purchasing Info Record
- C. Contract
- D. Production Version
Answer: D
NEW QUESTION 43
What must be used in the system to plan the requirements for different subcontractors separately?
Response:
- A. Production versions
- B. Planning plant
- C. Storage locations
- D. MRP areas
Answer: D
NEW QUESTION 44
What is the purpose of collective orders?
- A. To post production costs on a cost collector instead of the production order
- B. To post any component withdrawals single back flush with order confirmation
- C. To combine order management of co-products and by-products with the main product
- D. To manage production orders for an entire finished product on multiple levels
Answer: D
NEW QUESTION 45
How Is the bill of material (BOM) exploded when you use a BOM explosion number?
Please choose the correct answer.
Response:
- A. With respect to a common key date for product and each assembly
- B. With respect to a defined separate change status for product and each assembly
- C. With respect to defined separate key dates for product and each assembly
- D. With respect to a common change status for product and each assembly
Answer: C
NEW QUESTION 46
What is the difference between co-products and by-products?
- A. Only co-products are identified by a special item category in the bill of material (BOM).
- B. Only co-products can be manufactured in isolation from the main product.
- C. Only by-products have a zero inventory valuation.
- D. Only co-products appear in the process or production order settlement rule.
Answer: D
NEW QUESTION 47
How can you avoid order proposals for planned independent requirements with dates in the past?
There are 2 correct answers to this question.
Response:
- A. Set the requirements reduction indicator in the requirements class
- B. Use a planning strategy with requirements consumption
- C. Maintain adjustment parameter in the MRP group
- D. Reorganize planned independent requirements
Answer: C,D
NEW QUESTION 48
In which data object is the production line (Repetitive manufacturing relevant work center) maintained?
Please choose the correct answer.
Response:
- A. Bill of material
- B. Production version
- C. Cost collector
- D. Repetitive manufacturing profile
Answer: B
NEW QUESTION 49
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:
- A. Planning without final assembly (50)
- B. Make-to-order production (20)
- C. Production by lot size (30)
- D. Planning with final assembly (40)
Answer: A
NEW QUESTION 50
......