Verified AACE-PSP Exam Dumps PDF [2021] Access using DumpsQuestion
Try Best AACE-PSP Exam Questions from Training Expert DumpsQuestion
For more info read reference:
Planning & Scheduling Professional (PSP) Exam Certification Path
The certification path for the Planning & Scheduling Professional (PSP) Exam consists only of this Planning & Scheduling Professional (PSP) Examination. The applicants must fulfill the eligibility criteria of having at least 8 years of industry experience only or 4 years of industry experience plus 4 years of a related degree from a college.
NEW QUESTION 33
Which statement is true?
- A. Where compensability can be established, excusability is assumed.
- B. Where compensability can be established, excusabltity cannot be assumed.
- C. Where compensability cannot be established, excusability is assumed.
- D. Where compensability cannot be established, excusability is a given.
Answer: C
NEW QUESTION 34
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 10 days.
- B. 5 days.
- C. 0 days.
- D. 15 days.
Answer: B
NEW QUESTION 35
What was the original planned duration for Activity A through Activity G?
- A. 25.
- B. 24.
- C. 26.
- D. 28.
Answer: D
NEW QUESTION 36
The linear scheduling velocity diagram has the following two-axis:
- A. Time and rate of progress
- B. Time and location
- C. Location and crew size
- D. Time and crew size
Answer: A
NEW QUESTION 37
What is the remaining work duration of Active D?
- A. 8.
- B. 3.
- C. 4.
- D. 0
Answer: C
NEW QUESTION 38
Identify the late finish to develop plans and specs.
- A. 8 months.
- B. 7 months.
- C. 9 months.
- D. 10 months.
Answer: C
NEW QUESTION 39
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT
- A. Use gross building square footages. The pluses and minuses all average out.
- B. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
- C. Use the people responsible for performing the work as a resource to assign activity durations.
- D. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.
Answer: A
NEW QUESTION 40
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project objectives in terms of cost, schedule and quality measures
- B. Project contract between the contractor and owner
- C. Project deliverables
- D. Project justification
Answer: D
NEW QUESTION 41
If Activity E's duration changes to 4 months, what is the overall duration of the project.
- A. 22 months.
- B. 21 months.
- C. 19 months.
- D. 20 months.
Answer: D
NEW QUESTION 42
If all other work proceeds according to the Baseline plan, how many times will the critical path change?
- A. Does not change.
- B. 2.
- C. 3.
- D. 1.
Answer: A
NEW QUESTION 43
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. Certain activities in the critical path have no successors.
- B. The schedule is projecting an "early completion".
- C. The schedule has too much detail to reflect an accurate critical path.
- D. Different calendars are assigned to certain activities in the logical chain.
Answer: A
NEW QUESTION 44
How much Total Float does drafting the product manual have?
- A. 10 workdays.
- B. 15 workdays.
- C. 0 workdays.
- D. 5 workdays.
Answer: A
NEW QUESTION 45
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. The activities occur in series with a 15-day lag.
- B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- C. The activities run concurrently.
- D. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
Answer: A
NEW QUESTION 46
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 267 days
- B. 407 days
- C. 255 days
- D. 362 days
Answer: B
NEW QUESTION 47
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
- A. $289,000
- B. $299,000
- C. $271,000
- D. $139,000
Answer: A
NEW QUESTION 48
What problems can a soils engineer deal with on a project?
- A. Toxic soils.
- B. Archeological findings.
- C. Hidden subsurface conditions.
- D. Survey error.
Answer: C
NEW QUESTION 49
......
Latest 100% Passing Guarantee - Brilliant AACE-PSP Exam Questions PDF: https://www.dumpsquestion.com/AACE-PSP-exam-dumps-collection.html
Practice Examples and Dumps & Tips for 2021 Latest AACE-PSP Valid Tests Dumps: https://drive.google.com/open?id=192YiaGZbFfXF22L-Q1tFlF8tmpu4Vvqc