The certification path for the Planning & Scheduling Professional (PSP) Exam consists only of this Planning & Scheduling Professional (PSP) Examination. The applicants must fulfill the eligibility criteria of having at least 8 years of industry experience only or 4 years of industry experience plus 4 years of a related degree from a college.

 

NEW QUESTION 33
Which statement is true?

  • A. Where compensability can be established, excusability is assumed.
  • B. Where compensability can be established, excusabltity cannot be assumed.
  • C. Where compensability cannot be established, excusability is assumed.
  • D. Where compensability cannot be established, excusability is a given.

Answer: C

 

NEW QUESTION 34
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 10 days.
  • B. 5 days.
  • C. 0 days.
  • D. 15 days.

Answer: B

 

NEW QUESTION 35
What was the original planned duration for Activity A through Activity G?

  • A. 25.
  • B. 24.
  • C. 26.
  • D. 28.

Answer: D

 

NEW QUESTION 36
The linear scheduling velocity diagram has the following two-axis:

  • A. Time and rate of progress
  • B. Time and location
  • C. Location and crew size
  • D. Time and crew size

Answer: A

 

NEW QUESTION 37
What is the remaining work duration of Active D?

  • A. 8.
  • B. 3.
  • C. 4.
  • D. 0

Answer: C

 

NEW QUESTION 38
Identify the late finish to develop plans and specs.

  • A. 8 months.
  • B. 7 months.
  • C. 9 months.
  • D. 10 months.

Answer: C

 

NEW QUESTION 39
Activity durations are normally estimated in an intuitive and subjective way. All of the following will improve duration accuracy EXCEPT

  • A. Use gross building square footages. The pluses and minuses all average out.
  • B. Look at each activity independently and don't follow specific logic paths when assigning activity durations.
  • C. Use the people responsible for performing the work as a resource to assign activity durations.
  • D. Divide activities into smaller activities. This will increase activity detail and duration estimate accuracy.

Answer: A

 

NEW QUESTION 40
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

  • A. Project objectives in terms of cost, schedule and quality measures
  • B. Project contract between the contractor and owner
  • C. Project deliverables
  • D. Project justification

Answer: D

 

NEW QUESTION 41
If Activity E's duration changes to 4 months, what is the overall duration of the project.

  • A. 22 months.
  • B. 21 months.
  • C. 19 months.
  • D. 20 months.

Answer: D

 

NEW QUESTION 42
If all other work proceeds according to the Baseline plan, how many times will the critical path change?

  • A. Does not change.
  • B. 2.
  • C. 3.
  • D. 1.

Answer: A

 

NEW QUESTION 43
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. Certain activities in the critical path have no successors.
  • B. The schedule is projecting an "early completion".
  • C. The schedule has too much detail to reflect an accurate critical path.
  • D. Different calendars are assigned to certain activities in the logical chain.

Answer: A

 

NEW QUESTION 44
How much Total Float does drafting the product manual have?

  • A. 10 workdays.
  • B. 15 workdays.
  • C. 0 workdays.
  • D. 5 workdays.

Answer: A

 

NEW QUESTION 45
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities occur in series with a 15-day lag.
  • B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • C. The activities run concurrently.
  • D. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.

Answer: A

 

NEW QUESTION 46
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 267 days
  • B. 407 days
  • C. 255 days
  • D. 362 days

Answer: B

 

NEW QUESTION 47
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?

  • A. $289,000
  • B. $299,000
  • C. $271,000
  • D. $139,000

Answer: A

 

NEW QUESTION 48
What problems can a soils engineer deal with on a project?

  • A. Toxic soils.
  • B. Archeological findings.
  • C. Hidden subsurface conditions.
  • D. Survey error.

Answer: C

 

NEW QUESTION 49
......