The Best C-TS422-2021 Exam Study Material and Preparation Test Question Dumps [Q36-Q54]

Share

The Best C-TS422-2021 Exam Study Material and Preparation Test Question Dumps

Get Ready to Pass the C-TS422-2021 exam Right Now Using Our SAP Certified Application Associate Exam Package


SAP C-TS422-2021 certification exam is intended for professionals who work in the field of production planning and manufacturing, such as consultants, project managers, and application specialists. These professionals should have a minimum of one year of experience working with SAP S/4HANA production planning and manufacturing solutions. They should also have a solid understanding of the principles and concepts of production planning and manufacturing processes.

 

NEW QUESTION # 36
During production order creation, several valid production versions are found. How does the system choose the production version?

  • A. Alphanumeric or quota arrangement
  • B. Valid period or sale order
  • C. Lot size or material cost
  • D. Planned order or material number

Answer: A


NEW QUESTION # 37
In the Schedule Production app which setting can you make for the planning strategy?

  • A. Fitness level
  • B. Direction
  • C. Planning mode
  • D. Fixed pegging
  • E. Scheduling control

Answer: B,C,E


NEW QUESTION # 38
For what production type are production orders used?

  • A. Period and quantity-oriented production
  • B. Process manufacturing processes
  • C. Discrete manufacturing processes
  • D. Replenishment controlled by control cycles

Answer: C


NEW QUESTION # 39
When can the automatic material availability check occur in a production order?

  • A. At order settlement
  • B. At order creation
  • C. At order release
  • D. At order confirmation

Answer: B,C


NEW QUESTION # 40
Which time elements are part of a routing operation?

  • A. Wait time
  • B. Pick/pack time
  • C. Move time
  • D. Float before production
  • E. Queue time

Answer: A,B,E


NEW QUESTION # 41
What does the material type influence?

  • A. Which plant specific status is allowed
  • B. Which material master views can be maintained
  • C. Whether the material is produced in-house, procured externally or bouth
  • D. Which document types are allowed

Answer: B,C


NEW QUESTION # 42
If the stock level drops below the reorder stock in reorder point planning, what logic would the system use to trigger procurement?

  • A. Fill up to the reorder stock level
  • B. Fill up based on the lot size procedure
  • C. Fill up to the maximum stock level
  • D. Fill up to the safety stoc level

Answer: B


NEW QUESTION # 43
What happens to this dependent requirement when you convert the planned order into a production order?

  • A. They are converted into a production order.
  • B. They are converted into a schedule line.
  • C. They are converted into a planned order.
  • D. They are converted into a reservation.

Answer: D


NEW QUESTION # 44
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?

  • A. Consumption sequence procedure
  • B. Requirements type
  • C. Requirements profile
  • D. Order type

Answer: B


NEW QUESTION # 45
Which time elements are relevant for lead time scheduling of a production order?

  • A. Total replenishment lead time
  • B. Setup time
  • C. Float after production
  • D. Planned delivery time

Answer: C,D


NEW QUESTION # 46
In your project, you have several materials that are planned by different people. How can you assign the planning responsibility?

  • A. MRP group
  • B. MRP controller
  • C. MRP planning file
  • D. MRP type

Answer: B


NEW QUESTION # 47
What does it mean for the production planner when MRP works with infinite capacities?

  • A. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
  • B. MRP creates capacity requirements without checking the capacity of a work center.
  • C. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
  • D. MRP creates capacity requirements only if the work center has sufficient capacity.

Answer: B


NEW QUESTION # 48
You want to create a production order from a planned order. What methods could you use?

  • A. Combined conversion
  • B. Collective conversion
  • C. Partial conversion
  • D. Order release

Answer: B,C


NEW QUESTION # 49
Which SAP solutions support the supplier area in the portfolio of the Digital Value Network?

  • A. SAP Hybris
  • B. SAP Ariba
  • C. SAP Fieldglass
  • D. SAP Concur
  • E. SAP SuccessFactors

Answer: B,C,D


NEW QUESTION # 50
You want to use capacity availability checks for production orders. Which settings have to be made for this?

  • A. The PRT Availability Check must be set in the checking control.
  • B. A checking rule must be assigned in the checking control
  • C. An overall profile must be assigned in the checking control.
  • D. The Relevant for Finite Scheduling indicator must be set

Answer: C,D


NEW QUESTION # 51
Which chart types does the tabular planning table provide in SAP S/4HANA

  • A. Order (dispatched) chart
  • B. Work center capacities chart
  • C. Order (pool) chart
  • D. Capacity requirements chart

Answer: B,D


NEW QUESTION # 52
You have a schedule agreement whit a vendor. You want classic MRP to automatically create schedule lines in case of material shortage.
What must you do?

  • A. Set the creation indicator for purchase requisitions on initial screen of MRP run
  • B. Add the agreement to the quota arrangement and mark it for MRP revalance.
  • C. Set the creation indicator for delivery schedule lines on the initial screen of the MRP run.
  • D. Add the agreement to the source list and mark it for MRP revalance.

Answer: C,D


NEW QUESTION # 53
What are the possible results of a production planning run in Advanced Planning (PP/DS)?

  • A. Scheduling agreement schedule line
  • B. Production order
  • C. Stock transport order
  • D. Purchase requistion
  • E. Planned order

Answer: A,D,E


NEW QUESTION # 54
......

Get Special Discount Offer of C-TS422-2021 Certification Exam Sample Questions and Answers: https://www.dumpsquestion.com/C-TS422-2021-exam-dumps-collection.html

Enhance Your Career With Available Preparation Guide for C-TS422-2021 Exam: https://drive.google.com/open?id=1TOo2qJ0l8yiYP6nNEHbOKtKJVg7wjqMT